AN ORDINANCE APPROVING CONSTRUCTION CONTRACT - OUTFALL 061 & 062 RELIEF SEWER - RESOLUTION/WORK ORDER #76087 - $6,853,570.80 BETWEEN DUNIGAN BROTHERS AND THE CITY OF FORT WAYNE, INDIANA, IN CONNECTION WITH THE BOARD OF PUBLIC WORKS
| Bill Number: | S-17-02-01 | 1st District - Paul Ensley | Aye |
| Ordinance Number: | S-23-17 | 2nd District - Russ Jehl | Aye |
| Status: | Passed | 3rd District - Tom Didier | Aye |
| Introduction Date: | 2017-02-14 | 4th District - Jason Arp | Aye |
| Last Discussed: | 2017-02-21 | 5th District - Geoff Paddock | Aye |
| Date Passed: | 2017-02-28 | 6th District - Glynn Hines | Aye |
| Category: | Special | At Large - Michael Barranda | Aye |
| Committee: | City Utilities | At Large - John Crawford | Aye |
| Public Hearing: | At Large - Tom Freistroffer | Aye |