Bill Number S-20-01-28

AN ORDINANCE APPROVING PROFESSIONAL ENGINEERING SERVICES CONTRACT - THREE RIVERS PROTECTION & OVERFLOW REDUCTION TUNNEL (3RPORT) DEEP DEWATERING PUMP STATION PACKAGE FINAL DESIGN SERVICES - RESOLUTION/WORK ORDER #76003 - $627,930.00 BETWEEN BLACK & VEATCH CORPORATION AND THE CITY OF FORT WAYNE, INDIANA, IN CONNECTION WITH THE BOARD OF PUBLIC WORKS.

Agenda Committee Agenda Committee Discussion Video Formal Discussion Video

Bill Number: S-20-01-28 1st District - Paul Ensley Aye
Ordinance Number: S-25-20 2nd District - Russ Jehl Aye
Status: Passed 3rd District - Tom Didier Aye
Introduction Date: 2020-01-28 4th District - Jason Arp Aye
Last Discussed: 2020-02-11 5th District - Geoff Paddock Aye
Date Passed: 2020-02-11 6th District - Sharon Tucker Aye
Category: Special At Large - Glynn Hines Aye
Committee: City Utilities At Large - Michelle Chambers Aye
Public Hearing: At Large - Tom Freistroffer Aye