Bill Number S-19-10-22

AN ORDINANCE APPROVING CONSTRUCTION CONTRACT - CSO 31 & THIRD STREET PUMP STATION CONSOLIDATION SEWER - RESOLUTION/WORK ORDER #76467 - $8,557,000.00 BETWEEN KOKOSING INDUSTRIAL, INC. AND THE CITY OF FORT WAYNE, INDIANA, IN CONNECTION WITH THE BOARD OF PUBLIC WORKS

Agenda Committee Agenda Committee Discussion Video Formal Discussion Video

Bill Number: S-19-10-22 1st District - Paul Ensley Absent
Ordinance Number: S-133-19 2nd District - Russ Jehl Aye
Status: Passed 3rd District - Tom Didier Aye
Introduction Date: 2019-10-22 4th District - Jason Arp Aye
Last Discussed: 2019-11-12 5th District - Geoff Paddock Aye
Date Passed: 2019-11-12 6th District - Glynn Hines Aye
Category: Special At Large - Michael Barranda Aye
Committee: City Utilities At Large - John Crawford Aye
Public Hearing: At Large - Tom Freistroffer Aye

Associated Files