AN ORDINANCE APPROVING CONSTRUCTION CONTRACT - GETZ ROAD AND CONSTITUTION DRIVE INTERSECTION IMPROVEMENTS - RESOLUTION #0154A - WORK ORDER #0154A - ($222,677.00) BETWEEN E&B PAVING AND THE CITY OF FORT WAYNE, INDIANA IN CONNECTION WITH THE BOARD OF PUBLIC WORKS.
| Bill Number: | S-17-09-16 | 1st District - Paul Ensley | Aye |
| Ordinance Number: | S-118-17 | 2nd District - Russ Jehl | Aye |
| Status: | Passed | 3rd District - Tom Didier | Aye |
| Introduction Date: | 2017-09-26 | 4th District - Jason Arp | Aye |
| Last Discussed: | 2017-10-10 | 5th District - Geoff Paddock | Aye |
| Date Passed: | 2017-10-10 | 6th District - Glynn Hines | Absent |
| Category: | Special | At Large - Michael Barranda | Aye |
| Committee: | Public Works | At Large - John Crawford | Aye |